Shifting builds: project delays and the validity of EIA

21st July 2022


When a construction project is delayed, are the environmental impact assessment’s findings still valid? Ellen Smith reports

A consultant carrying out a construction programme environmental impact assessment (EIA) under the Town and Country Planning (EIA) Regulations 2017 must consider the intensity and type of construction activity in order to assess construction effects, and the programme’s completion year in order to assess operational effects. EIAs often consider construction programmes provided by applicants before contractors have been appointed, so are subject to change. However, consultants should assume that most planning applications have a three-to-five-year implementation period, and this should be considered as a minimum in the construction programme.

If there are unknowns in the construction programme, assumptions should be made clear in the environmental statement (ES). Assumptions in the construction programme should aim to provide a reasonable worst case – for example, assuming the nearest potential location of construction plant in proximity to surrounding receptors, and the overlapping of construction activities. While programming for the works may be subject to modification, there has usually been sufficient planning to enable the likely significant environmental effects to be identified and assessed.

When an applicant needs to seek planning permission to change a scheme’s design or phasing, a change in construction programme can be addressed through further environmental information, such as an ES addendum. This could require the assessment of a further interim scenario, should there be a significant delay in delivering part of the proposed development, resulting in part-occupation.

Otherwise, in terms of construction traffic it could be considered that the original dates in the ES present a worst-case assessment for air quality, noise and traffic, as the UK vehicle fleet is projected to improve. Other environmental topics, such as wind, daylight and sunlight, flood risk and ecology are unlikely to be affected by a change in construction programme – unless there is a significant change in phasing, in which case temporary mitigation measures may be required (such as temporary screening if there are wind safety concerns).

Cumulative concerns

One issue with a change in construction programme is the assessment of cumulative effects. A proposed development will not cumulatively interact with other identified cumulative developments during construction if a proposed development or cumulative scheme is delayed.

To provide a worst-case assessment, and where information on the construction programmes of other developments is unavailable, reasonable assumptions should be set out in the ES, such as the extent to which the cumulative schemes would have overlapping construction programmes.

Any new schemes gaining consent following permission for the proposed development – and not previously identified in the EIA as coming forward – should be assumed to have assessed the proposed development in their own cumulative assessments.

So a change in construction programme can be tricky for EIA, particularly when it comes to the cumulative assessment. The consultant should take care to set out the reasonable assumptions made in the assessments, such as the assumption that the cumulative schemes would have their own construction environmental management plans or construction logistics plans in place. Limitations, such as a lack of available information on a construction programme, should also be reported in the ES.

EIAs cannot consider every outcome, but including clear assumptions and limitations allows the appropriate identification of likely significant effects. Whether an EIA is valid when the original construction date has changed should be decided on a case-by-case basis.

Ellen Smith, PIEMA is principal EIA consultant at Waterman Infrastructure & Environmental.

Image credit | Shutterstock

Subscribe

Subscribe to IEMA's newsletters to receive timely articles, expert opinions, event announcements, and much more, directly in your inbox.


Transform articles

New guidance maps out journey to digital environmental assessment

IEMA’s Impact Assessment Network is delighted to have published A Roadmap to Digital Environmental Assessment.

2nd April 2024

Read more

Lisa Pool on how IEMA is shaping a sustainable future with impact assessment

27th November 2023

Read more

IEMA responded in September to the UK government’s consultation on the details of the operational reforms it is looking to make to the Nationally Significant Infrastructure Projects (NSIP) consenting process as put forward in the NSIP reform action plan (February 2023).

24th November 2023

Read more

Members of IEMA’s Impact Assessment Network Steering Group have published the 17th edition of the Impact Assessment Outlook Journal, which provides a series of thought pieces on the policy and practice of habitats regulations assessment (HRA).

26th September 2023

Read more

In July, we published the long-awaited update and replacement of one of IEMA’s first published impact assessment guidance documents from 1993, Guidelines for the Environmental Assessment of Road Traffic.

1st August 2023

Read more

Are we losing sight of its intended purpose and what does the future hold for EIA? Jo Beech, Tiziana Bartolini and Jessamy Funnell report.

15th June 2023

Read more

Luke Barrows and Alfie Byron-Grange look at the barriers to adoption of digital environmental impacts assessments

1st June 2023

Read more

Susan Evans and Helen North consider how Environmental Statements can be more accessible and understandable

1st June 2023

Read more

Media enquires

Looking for an expert to speak at an event or comment on an item in the news?

Find an expert

IEMA Cookie Notice

Clicking the ‘Accept all’ button means you are accepting analytics and third-party cookies. Our website uses necessary cookies which are required in order to make our website work. In addition to these, we use analytics and third-party cookies to optimise site functionality and give you the best possible experience. To control which cookies are set, click ‘Settings’. To learn more about cookies, how we use them on our website and how to change your cookie settings please view our cookie policy.

Manage cookie settings

Our use of cookies

You can learn more detailed information in our cookie policy.

Some cookies are essential, but non-essential cookies help us to improve the experience on our site by providing insights into how the site is being used. To maintain privacy management, this relies on cookie identifiers. Resetting or deleting your browser cookies will reset these preferences.

Essential cookies

These are cookies that are required for the operation of our website. They include, for example, cookies that enable you to log into secure areas of our website.

Analytics cookies

These cookies allow us to recognise and count the number of visitors to our website and to see how visitors move around our website when they are using it. This helps us to improve the way our website works.

Advertising cookies

These cookies allow us to tailor advertising to you based on your interests. If you do not accept these cookies, you will still see adverts, but these will be more generic.

Save and close