Politics and poor judgement in screening opinions

14th November 2013


Related Topics

Related tags

  • Consultancy ,
  • Construction

Author

IEMA

Chris Rochfort, from MWH, discusses a planning authority's screening opinion where the applicant felt that the legislation had been incorrectly interpreted, and that local pressures had influenced the decision

Water and sewerage pipeline projects are sometimes subject to environmental impact assessment (EIA). Circular 02/99 states that pipelines greater1 hectare in size are Schedule 2 developments, with projects more than 5km in length and those affecting “sensitive sites” as defined by the EIA Regulations, more likely to trigger an EIA.

MWH, on behalf of a water utility, undertook an EIA screening for a project aimed at alleviating sewer flooding in the basements of 300 properties. The solution involved significant works in two local parks; the only suitably large and open areas in the high density location. The scheme included underground stormwater storage shafts, small buildings and hard/soft landscaping in each park. In addition, a new 400m, 2.5m diameter tunnel sewer and 1.1km of sewer upgrades were required.

As statutory undertakers, water companies benefit from significant permitted development rights under Part 16, Class A (a) of the Town and Country Planning (General Permitted Development) Order 1995. However, permitted development rights do not apply if the development is screened as EIA development, instead requiring a planning application.

Screening for EIA

The scheme is a Schedule 2 development because the project is larger than 1ha. The case against the need for EIA, made the following arguments :

  • The reasons to require an EIA on a Schedule 2 development, as set out in paragraph 33 of Circular 02/99, did not apply.
  • The scheme’s temporary nature and less intrusive construction methods lessened the significance of any residual environmental effects.
  • Circular 02/99, section A28 states: “For underground pipelines... EIA is more likely to be required for any pipeline over 5km long. EIA is unlikely to be required for pipelines laid underneath a road, or for those installed entirely by means of tunnelling.” In this case, the new sewers total approximately 1.5km, with the majority laid underneath road, or by means of tunnelling.
  • One of the parks, a site of importance for nature conservation (SINC), related to a small manmade wildflower meadow, which did not meet the criteria for sensitive areas.
  • Paragraph 65 of Circular 02/99 states: “Local planning authorities are reminded… to determine the significance or otherwise of the likely environmental effects of the proposed development, rather than to judge its planning merits. They should, therefore, make every effort to minimise disruption and delay, particularly … for essential improvements to public water and sewage treatment systems...”

Despite these compelling arguments, the local planning authority concluded an EIA was required, for the following reasons:

  1. “Taking into account the extent, nature, complexity and duration of the proposed works, and the location in a densely populated urban environment, the development scheme is likely to have significant effects on the environment, particularly in terms of pollution and nuisance (including traffic) during the construction phases of the development.”
  2. “Taking into account the scale and extent of the proposed works and their location within parks (including the SINC) and the underground tunnelling proposed, the scheme is likely to generate significant environmental impacts in terms of ecosystems and changes to water levels.”

While the basis for the first reason is understandable, the SINC cannot be used as a basis for an EIA being required. Additionally, the works are all in London Clay, an aquiclude (a barrier to groundwater flow), and more than 1km from the nearest watercourse, meaning that no impact on water was expected.

Interpretation of law

The project team felt that the decision had to be challenged because it was felt to be an incorrect interpretation of the environmental risks, the EIA Regulations and Circular 02/99 and it risked setting a precedent for similar schemes. Carrying out an EIA would also delay the programme and increase costs.

The local planning authority confirmed that consultation with residents groups and councillors had uncovered significant opposition to the project, mainly by residents not benefitting from the project. Residents had also raised the issue of EIA with the councillors, while earlier informal comments from the case officer had suggested that EIA was not an area of concern.

The project team was of the opinion that the council was nervous of a judicial review if an EIA was not requested, and so exaggerated the justification for their decision; as was evident in their second reason . Consequently, a written request was made to the secretary of state for an EIA screening direction pursuant to Regulation 5(7b) of the EIA Regulations.

The secretary of state dismissed the local planning authority’s first reason for requesting an EIA, stating that he was “not persuaded that there is specific evidence to suggest that this is a development with particularly complex and potentially hazardous environmental effects necessitating an environmental statement. While some noise and traffic disruption is likely, this would be temporary.”

With respect to second reason given by the planning authority, the secretary of state noted: “The site does not fall within or near to a ‘sensitive area’ … or in an area covered by other statutory designations protecting environmentally sensitive interests.

“There is insufficient evidence to support the assertion that the potential impact of the works … may have a significant effect on the ecosystem and on water levels ... these matters can be addressed through the planning process.”

Lessons learned

When reviewing the scheme, the case officer should not have asked for an EIA, and may have been influenced into making use of certain grey areas in Circular 02/99 to justify the need for an assessment.

In reality, political influence in EIA screening decisions is probably not uncommon. The positive or negative view that influential staff in a local planning authority hold in relation to a scheme, or the level of concern about potential judicial review threats, might, in some cases, influence the EIA screening decision. Nonetheless, planning authorities must follow the instructions in Circular 02/99 and not be selective in which elements to embrace or ignore.

Thankfully, seeking a screening direction from the secretary of state can provide the common sense required. Perhaps the long-awaited replacement to Circular 02/99 may erase some of the grey areas?


This article was written as a contribution to the EIA Quality Mark’s commitment to improving EIA practice.

Chris Rochfort, MIEMA CEnv, is a principal environmental consultant at MWH. [email protected]

Subscribe

Subscribe to IEMA's newsletters to receive timely articles, expert opinions, event announcements, and much more, directly in your inbox.


Transform articles

New guidance maps out journey to digital environmental assessment

IEMA’s Impact Assessment Network is delighted to have published A Roadmap to Digital Environmental Assessment.

2nd April 2024

Read more

Lisa Pool on how IEMA is shaping a sustainable future with impact assessment

27th November 2023

Read more

IEMA responded in September to the UK government’s consultation on the details of the operational reforms it is looking to make to the Nationally Significant Infrastructure Projects (NSIP) consenting process as put forward in the NSIP reform action plan (February 2023).

24th November 2023

Read more

Members of IEMA’s Impact Assessment Network Steering Group have published the 17th edition of the Impact Assessment Outlook Journal, which provides a series of thought pieces on the policy and practice of habitats regulations assessment (HRA).

26th September 2023

Read more

In July, we published the long-awaited update and replacement of one of IEMA’s first published impact assessment guidance documents from 1993, Guidelines for the Environmental Assessment of Road Traffic.

1st August 2023

Read more

Are we losing sight of its intended purpose and what does the future hold for EIA? Jo Beech, Tiziana Bartolini and Jessamy Funnell report.

15th June 2023

Read more

Luke Barrows and Alfie Byron-Grange look at the barriers to adoption of digital environmental impacts assessments

1st June 2023

Read more

Susan Evans and Helen North consider how Environmental Statements can be more accessible and understandable

1st June 2023

Read more

Media enquires

Looking for an expert to speak at an event or comment on an item in the news?

Find an expert

IEMA Cookie Notice

Clicking the ‘Accept all’ button means you are accepting analytics and third-party cookies. Our website uses necessary cookies which are required in order to make our website work. In addition to these, we use analytics and third-party cookies to optimise site functionality and give you the best possible experience. To control which cookies are set, click ‘Settings’. To learn more about cookies, how we use them on our website and how to change your cookie settings please view our cookie policy.

Manage cookie settings

Our use of cookies

You can learn more detailed information in our cookie policy.

Some cookies are essential, but non-essential cookies help us to improve the experience on our site by providing insights into how the site is being used. To maintain privacy management, this relies on cookie identifiers. Resetting or deleting your browser cookies will reset these preferences.

Essential cookies

These are cookies that are required for the operation of our website. They include, for example, cookies that enable you to log into secure areas of our website.

Analytics cookies

These cookies allow us to recognise and count the number of visitors to our website and to see how visitors move around our website when they are using it. This helps us to improve the way our website works.

Advertising cookies

These cookies allow us to tailor advertising to you based on your interests. If you do not accept these cookies, you will still see adverts, but these will be more generic.

Save and close