Demolishing preconceptions

26th March 2021


Web p24 rubble shutterstock 1235608855

Related Topics

Related tags

  • Construction ,
  • Planning ,
  • Transport

Author

Robert Askew

Thomas Cleary, Greg Lewis and Daniel Brown share how the Costain-Skanska Joint Venture team is applying an environmental approach to HS2 demolition work around Euston Station

On HS2 Enabling Works Contract-South, the Costain-Skanska Joint Venture (CSjv) team and its supply chain have placed the environment front and centre of decision-making in order to push development in key areas around selection of equipment, material reuse and protection screen designs.

The location of the demolition work involved in the London leg of HS2 Phase One made it imperative for the team to reduce the impact of associated noise, vibration and air quality on the local community. The Euston Approaches Demolitions team identifi ed several ways it could reduce the impact of activities through the full integration of environmental specialists and constraints at the pre-planning stage, informing procurement, selection criterion and overall sequencing and methodology.

Material re-use

A key challenge from the demolition work was how CSjv would manage the volume of waste being produced. This was particularly difficult due to the congested road networks surrounding CSjv’s sites, based primarily around Euston Station in the London Borough of Camden. One of the first demolition projects was a former warehouse and a university architecture building. Working with the air quality specialist and the environment team, a procurement selection criterion was devised to reward those who submitted a proposal in which demolition arising would be retained on site and crushed into usable 6F2 (engineered fill material). Despite being constrained on all sides, with very little room for manoeuvre, the supplier John F Hunt delivered a top-down solution that crushed more than 70% of the material on the footprint.

This is now practice across the contract, and through a workshop on designing out waste we developed a strategy of crushing demolition arisings into aggregates for re-use on site under the WRAP Quality Protocol. This was used to create temporary vehicle access ramps, crane mats and haul roads, as well as being deployed as backfill to structures and platforms in order to facilitate the main works civils contract.

This approach has resulted in 175,000 tonnes of demolition arisings being crushed. This has saved more than 1,500 tonnes of CO2 equivalent (CO2e), compared to waste removal and subsequent importing of recycled aggregate, and taken away the need for waste removal and subsequent material delivery, saving nearly £5m. The strategy saved 39,000 vehicle movements associated with waste removal and material delivery, significantly reducing impacts on local roads and air quality.

The team’s co-operation with HS2 and the Environment Agency allowed multiple work package areas to be treated as a ‘single site’, facilitating the transfer, storage and re-use of recovered materials. This enabled further collaboration with Skanska’s IP Central Euston works and the SCS Main Works contract on adjacent sites.

"The location of the work has made it imperative for the team to reduce noise, vibration and air quality impacts"

Equipment selection and demolition screens

A large element of demolition is the equipment used to protect the surrounding environment. Traditionally, in an urban environment, a top-down demolition method would be used, with scaffold encapsulation to provide protection from debris. This involves lifting smaller machines (depending on the strength of the building) onto the roof and demolishing the building using percussive techniques (such as breakers), all behind a scaffold screen.

To minimise the noise and vibration of demolition, the CSjv team at Regent’s Park Estate pushed to reduce the use of scaffolding as a screen where possible. This meant larger machines could be used for demolition without fear of causing uncontrolled collapse. The team designed a bespoke curtain that could be hung from a crane and follow the path of demolition as it progressed. The curtain was developed with a built-in water supply to nozzles in the beam at the top, providing dust suppression.

The use of the heavier high-reach excavator allowed for a pulveriser attachment that was large enough to crush the concrete, rather than a breaker attachment. A top-down method would have required demolition with breakers, as the capacity of the floor slabs limits the size of the machines that can be placed on them. When modelling the predicted noise levels for the two methods, we found noise levels when using pulverising attachments to be 12dB less at 10m away than noise levels when using breaking attachments.

The lessons learnt are being transferred to the next works package, where the high reach excavator will be used again. This time there is a greater constraint on the works in the form of the railway approaches into Euston Station. The team has worked hard to ensure a long reach excavator can be used, to maintain the reduction of noise and vibration. Demolition with the high-reach cannot be done with a full scaffold wrap, but we needed a more predictable screening system than the ‘curtain’.

A shipping container screen has been designed for the power signal box demolition work, and is to be used in tandem with the demolition curtain (see above right). The fully enclosed container screen design gives Network Rail the confidence that passage of trains will not be aff ected, and gives CSjv and HS2 a more sustainable approach.

Thomas Cleary is project manager, CSjv.

Greg Lewis is senior environmental adviser, CSjv.

Daniel Brown is site agent, CSjv.

Image credit: Shutterstock

Subscribe

Subscribe to IEMA's newsletters to receive timely articles, expert opinions, event announcements, and much more, directly in your inbox.


Transform articles

The time is now

Dr Julie Riggs issues a call to arms to tackle a modern-day human tragedy

15th March 2024

Read more

The UK government’s carbon capture, usage and storage (CCUS) strategy is based on optimistic techno-economic assumptions that are now outdated, Carbon Tracker has warned.

13th March 2024

Read more

Multinational corporations are undermining their net-zero commitments with excessive air travel and no plans to reduce ‘the low hanging fruit’ of carbon footprints, a study by Transport & Environment has found.

13th March 2024

Read more

Large businesses across the world are avoiding climate action due to fear they will be called out for getting their work wrong, according to a new Carbon Trust report.

29th February 2024

Read more

A thought-provoking discussion on how storytelling can change the world took place in Central London last night, alongside an exclusive sneak preview of an upcoming IEMA film series.

29th February 2024

Read more

The UK’s net-zero economy grew 9% last year while delivering higher paid jobs than average and attracting billions of pounds in private investment, analysis by CBI Economics has uncovered.

28th February 2024

Read more

A consortium including IEMA and the Good Homes Alliance have drafted a letter to UK government ministers expressing disappointment with the proposed Future Homes Standard.

26th February 2024

Read more

IEMA and the Institute and Faculty of Actuaries (IFoA) have today published up-to-date guidance to help companies and individuals understand climate-related financial information.

22nd February 2024

Read more

Media enquires

Looking for an expert to speak at an event or comment on an item in the news?

Find an expert

IEMA Cookie Notice

Clicking the ‘Accept all’ button means you are accepting analytics and third-party cookies. Our website uses necessary cookies which are required in order to make our website work. In addition to these, we use analytics and third-party cookies to optimise site functionality and give you the best possible experience. To control which cookies are set, click ‘Settings’. To learn more about cookies, how we use them on our website and how to change your cookie settings please view our cookie policy.

Manage cookie settings

Our use of cookies

You can learn more detailed information in our cookie policy.

Some cookies are essential, but non-essential cookies help us to improve the experience on our site by providing insights into how the site is being used. To maintain privacy management, this relies on cookie identifiers. Resetting or deleting your browser cookies will reset these preferences.

Essential cookies

These are cookies that are required for the operation of our website. They include, for example, cookies that enable you to log into secure areas of our website.

Analytics cookies

These cookies allow us to recognise and count the number of visitors to our website and to see how visitors move around our website when they are using it. This helps us to improve the way our website works.

Advertising cookies

These cookies allow us to tailor advertising to you based on your interests. If you do not accept these cookies, you will still see adverts, but these will be more generic.

Save and close